Weekly Statistical Data on Maintenance Shutdowns of Propylene Oxide Plants in China

Published on 2026-11-06

Table: Domestic Propylene Oxide Plant Maintenance Schedule – November 6, 2026

Region Company Name Capacity (10k tons/year) Plant Status
Northeast Hangjin Technology 12 The 40,000-ton small unit experienced a fault on September 10 and is undergoing maintenance at half load; this may continue until the end of the month. The large unit is operating normally at full load.
North China Tianjin Bohua Chemical 20 Operating at approximately 90% load.
Tianjin Petrochemical 15 Operating at approximately 90% load.
Shandong Binzhou Chemical (Binhua) 28 Operating normally at full load. The 80,000-ton Dongrui unit shut down for maintenance starting November 3, with downstream polyether units synchronized; expected duration is 14 days.
Shandong Xinyue 30 Operating at near-full load. Downstream polyether units are gradually shutting down for upgrades from October 15 to November 25.
Shida Shenghua 7 Operating normally at full load.
Wanhua Chemical 154 Units 1, 2, and 4 are operating at slightly reduced loads. Unit 3 shut down for maintenance on October 27, with an estimated duration of around 20 days; specific timing is pending confirmation.
Shandong Jinling 16 Returned to normal full-load operation on November 4.
Shandong Sanyue 32 One production line shut down on October 29 for column cleaning; recovery is expected around mid-month.
Dongying Huatai 8 Operating normally at full load.
Zhonghai Fine Chemical 8 Shut down.
Qixiang Tengda 30 Operating at approximately 60–70% load.
Jincheng Petrochemical 30 Shut down.
Lihuayi Weiyuan 30 Operating normally at full load.
Binhua New Materials 24 Operating normally at full load.
Minxiang Chemical 15 Shut down on February 13, 2026; restart time pending confirmation.
Dongming Guoen 8 Shut down on December 21, 2025; potential restart planned for November 10, but details are pending confirmation.
Lianhong Gerun 30 Operating at approximately 70–80% load.
East China Jinling Huntsman 24 Operating normally at full load.
Ningbo Haian 57 Phase 1 operating at approximately 90% load. Phase 2 shut down for maintenance on September 24, 2025.
Zhenhai Refining & Chemical 30 Operating at approximately 90% load.
Hongbaoli 16 Shut down.
Jiangsu Fuqiang 10 Shut down.
Taixing Yida 15 Shut down.
Jiahong New Materials 40 Operating at approximately 70–80% load.
Zhejiang Petrochemical 27 Operating at 70–80% load. Annual maintenance tentatively scheduled to start on November 16 for 50 days, with downstream polyether units synchronized.
Ruiheng New Materials 40 Operating at approximately 50% load.
Shenghong Petrochemical 20 Shut down for maintenance on May 28; restart time pending confirmation.
South China Sinochem Quanzhou 20 Operating at approximately 90% load.
Guangxi Petrochemical 27 Operating at approximately 60% load.
Central China Sinopec Changling 10 Operating normally at full load.

Data Source: Chempricehub Information