Weekly Statistical Data on Maintenance of Propylene Oxide (PO) Plants in China

Published on 2026-10-23

Table 2026-10-23 Domestic Propylene Oxide (PO) Plant Maintenance Schedule

Region Enterprise Name Capacity (10,000 tons/year) Unit Status
Northeast Hangjin Technology 12 The 40,000-ton unit experienced a malfunction on Sept. 10 and is undergoing maintenance at half load, potentially continuing until year-end; the large unit is operating normally at full capacity.
North China Tianjin Bohua Chemical 20 Operating at approximately 90% load.
Tianjin Petrochemical 15 Operating normally at full capacity.
Shandong Binzhou Chemical (Binhua) 28 Operating normally at full capacity. Dongrui’s 80,000-ton unit is tentatively scheduled for shutdown and maintenance in November, with downstream polyether units synchronously halted for an estimated 14 days.
Shandong Xinyue 30 Operating at near-full capacity. Downstream polyether units will undergo sequential shutdowns for upgrades from Oct. 15 to Nov. 25.
Shida Shenghua 7 Operating normally at full capacity.
Wanhua Chemical 154 Phases 1–4 are operating at slightly reduced loads. Phase 3 is tentatively scheduled for a shutdown of over 20 days starting Oct. 25; specifics pending confirmation.
Shandong Jinling 16 Load reduced to approx. 75% starting Oct. 20; gradually shutting down completely by Oct. 23. Restart planned for Nov. 3.
Shandong Sanyue 32 Shut down for maintenance on Oct. 14; gradually returning to full capacity this week.
Dongying Huatai 8 Operating at half load as of Oct. 15; returned to full capacity on Oct. 19.
Zhonghai Fine Chemical 8 Unit shut down.
Qixiang Tengda 30 Operating at approx. 60% load.
Jincheng Petrochemical 30 Unit shut down.
Liuhua Yiweiyuan 30 Operating normally at full capacity.
Binhua New Materials 24 Operating normally at full capacity.
Minxiang Chemical 15 Shut down on Feb. 13, 2026; restart time TBD.
Dongming Guoen 8 Shut down on Dec. 21, 2025.
Lianhong Gerun 30 Operating at 70–80% load.
East China Nanjing Huntsman 24 Operating at approx. 80% load.
Ningbo Hai'an 57 Phase 1 operating at approx. 90% load. Phase 2 shut down for maintenance on Sept. 24, 2025.
Zhenhai Refining & Chemical 30 Operating at approx. 90% load.
Hongbaoli 16 Unit shut down.
Jiangsu Fuqiang 10 Unit shut down.
Taixing Yida 15 Unit shut down.
Jiahong New Materials 40 Operating at approx. 70–80% load.
Zhejiang Petrochemical 27 Operating at 70–80% load. Annual maintenance tentatively scheduled for early November.
Ruiheng New Materials 40 Load slightly reduced to approx. 50%.
Shenghong Petrochemical 20 Shut down for maintenance on May 28; restart time TBD.
South China Sinochem Quanzhou 20 Operating at approx. 90% load.
Guangxi Petrochemical 27 Operating at 60% load.
Central China Sinopec Changling 10 Operating normally at full capacity.

Data Source: Chempricehub Information