Domestic Major Pure Benzene Plant Maintenance Schedule (Oct 30 – Nov 5, 2026)

Published on 2026-11-05
Enterprise Maintenance Unit Capacity Start Date End Date Duration (Days) Weekly Loss Reason
Jiboh Petrochemical Cracking 7 2025-10-10 - - 0.15 Unplanned
Zhongyuan Ethylene Cracking 4 2025-11-05 - Planned Shutdown 0.09 Planned Shutdown
CNOOC Daxie Reforming 22 2025-11-05 - - 0.46 Unplanned
Youtai Petrochemical Reforming 2 2025-12-25 - - 0.03 Unplanned
Tianjin INEOS Aromatics Extraction 20 2026-03-25 - - 0.43 Feedstock Supply
Hainan Refining & Chemical No. 1 Aromatics 15 2026-06-30 2026-11-30 154 0.32 Extended Maintenance
Zhanjiang Dongxing Whole Plant 6 2026-06-08 2026-11-30 175 0.12 Unplanned
CNOOC Shell No. 1 Cracking Unit 23 2026-09-01 2026-11-30 90 0.48 Planned
Anqing Petrochemical Reforming 16 2026-09-02 2026-11-05 64 0.34 Planned
Puyang Zhonghui Phase II 18 2026-09-26 2026-11-26 61 0.38 Unplanned
Yantai Wanhua Cracking 15 2026-10-10 2026-12-10 61 0.32 Planned
Maoming Petrochemical Reforming 16 2026-10-12 2026-12-12 61 0.33 Planned
Shanghai Petrochemical Aromatics, Small-scale Cracking 17 2026-11-01 2026-12-31 60 0.26 Planned
Total 3.69

Petroleum benzene production stood at 440,400 tonnes. This represents a decrease of 1,800 tonnes compared to the previous period, corresponding to a change of -0.41%. The capacity utilization rate was 72.68%, down by 0.30 percentage points from the previous period. During this cycle, units such as the reforming plant at Anqing Petrochemical restarted, while facilities including the small-scale cracking unit at Shanghai Petrochemical shut down.